Rakesh can do a work in 20 days , Vasant in 15 days and Ravi in 10 days . They…

2025

Rakesh can do a work in 20 days , Vasant in 15 days and Ravi in 10 days . They all start the work together, but Rakesh leaves after 4 days and Vasant leaves 3 days before the work is completed. In how many days is the work completed ?

  1. A.

    6

  2. B.

    7

  3. C.

    8

  4. D.

    4

Attempted by 54 students.

Show answer & explanation

Correct answer: A

Ans: 6

Let the work is completed in x days, then

Rakesh's 4 day work + Vasant's (x-3) days work + Ravi's

x day work = 1

=> 4/20 + (x - 3) / 15 + x / 10 = 1

=> 10x / 60 = 1

=> x = 6