Rajiv can do a piece of work in 10 days, Venky in 12 days and Ravi in 15 days.…

2024

Rajiv can do a piece of work in 10 days, Venky in 12 days and Ravi in 15 days. They all start the work together, but Rajiv leaves after 2 days and Venky leaves 3 days before the work is completed. In how many days is the work completed?

  1. A.

    5

  2. B.

    6

  3. C.

    9

  4. D.

    7

Attempted by 637 students.

Show answer & explanation

Correct answer: D

Answer: 7

Step-by-step solution:

  • Work rates: Rajiv = 1/10 per day, Venky = 1/12 per day, Ravi = 1/15 per day.

  • If the job finishes in x days, Rajiv works 2 days → contribution = 2/10.

  • Venky leaves 3 days before finish, so he works x - 3 days → contribution = (x - 3)/12.

  • Ravi works the whole time x days → contribution = x/15.

  • Total work = 1, so set up the equation: 2/10 + (x - 3)/12 + x/15 = 1.

  • Clear denominators by multiplying both sides by 60: 12 + 5x - 15 + 4x = 60.

  • Simplify: 9x - 3 = 60 → 9x = 63 → x = 7.

  • Therefore, the work is completed in 7 days.