The ratio of efficiency of A is to C is 5:3 . The ratio of number of days…
2024
The ratio of efficiency of A is to C is 5:3 . The ratio of number of days taken by B is to C is 2:3 . A takes 6 days less than C, when A and C completes the work individually . B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is :
- A.
6
- B.
4
- C.
5
- D.
3
Attempted by 40 students.
Show answer & explanation
Correct answer: A