A alone can do a piece of work in 10 days, B alone in 12 days ,C alone in 15…

2024

A alone can do a piece of work in 10 days, B alone in 12 days ,C alone in 15 days .If all start work at same day . A works for 2 days and C leaves before 3 days of remaining work. In how many days work will finish ?

  1. A.

    19/3

  2. B.

    20/3

  3. C.

    7

  4. D.

    22/3

Attempted by 750 students.

Show answer & explanation

Correct answer: B

Key idea: let x be the total number of days to finish the work. A works for 2 days, B works for x days, and C leaves 3 days before completion, so C works (x - 3) days.

  • A's rate = 1/10 work per day

  • B's rate = 1/12 work per day

  • C's rate = 1/15 work per day

Write the total-work equation:

2*(1/10) + x*(1/12) + (x - 3)*(1/15) = 1

Multiply both sides by 60 (LCM of 10, 12, 15):

12 + 5x + 4(x - 3) = 60

Simplify: 12 + 5x + 4x - 12 = 60 → 9x = 60 → x = 20/3

Therefore, the work finishes in 20/3 days (approximately 6.67 days).