A man can do a work in 10 days. The man along with a boy can do the same work…
2024
A man can do a work in 10 days. The man along with a boy can do the same work in 8 days. What is the ratio of efficiencies of work of the man and the boy?
Answer: C. 4:1 — ConceptWork rate is the fraction of a job completed per unit time, so for a person who finishes a job in T days, the rate is 1/T job per day. When two people…
- A.
2:1
- B.
3:1
- C.
4:1
- D.
5:1
Attempted by 2 students.
Show answer & explanation
Correct answer: C
Concept
Work rate is the fraction of a job completed per unit time, so for a person who finishes a job in T days, the rate is 1/T job per day.
When two people work together, their individual rates add. Therefore, an unknown rate can be found by subtracting a known individual rate from the combined rate.
Application
The man completes the work in 10 days, so his rate is 1/10 of the work per day.
Together, the man and the boy complete the work in 8 days, so their combined rate is 1/8 of the work per day.
The boy’s rate is the combined rate minus the man’s rate: 1/8 − 1/10 = (5 − 4)/40 = 1/40 of the work per day.
Hence, the ratio of the man’s efficiency to the boy’s efficiency is (1/10):(1/40). Multiplying both terms by 40 gives 4:1.
Cross-check
Take the total work as 40 units. The man does 4 units per day and the boy does 1 unit per day; together they do 5 units per day and finish 40 units in 8 days. The man alone finishes the same work in 10 days.
Result
Therefore, the efficiency ratio of the man to the boy is 4:1.