15 men working 8 hours per day complete a piece of work in 18 days. To…

2024

15 men working 8 hours per day complete a piece of work in 18 days. To complete the same work in 6 days, working 12 hours a day, the number of men required will be:

Answer: D. 30 menTo solve this problem, we use the concept of man-hours. The total work done remains constant. We can equate the product of men, days, and hours for both…

  1. A.

    24 men

  2. B.

    26 men

  3. C.

    28 men

  4. D.

    30 men

Attempted by 14 students.

Show answer & explanation

Correct answer: D

To solve this problem, we use the concept of man-hours. The total work done remains constant. We can equate the product of men, days, and hours for both scenarios: M1 × D1 × H1 = M2 × D2 × H2. Substituting the given values: 15 × 18 × 8 = M2 × 6 × 12. Simplifying the left side gives 2160 man-hours. The right side becomes M2 × 72. Dividing both sides by 72, we find M2 = 30. Therefore, 30 men are required.