If a software project has 2000 lines of code (LOC) and the average…
PYQ UGC NET 2024
If a software project has 2000 lines of code (LOC) and the average productivity rate is 10 LOC per person-hour, how many person-hours are required to complete the project ?
- A.
100
- B.
150
- C.
200
- D.
250