The number of function points of a proposed system is calculated as 500.…
PYQ UGC NET 2016
The number of function points of a proposed system is calculated as 500. Suppose that the system is planned to be developed in Java and the LOC/FP ratio of Java is 50. Estimate the effort (E) required to complete the project using the effort formula of basic COCOMO given below :
E = a(KLOC)b
Assume that the values of a and b are 2.5 and 1.0 respectively.
- A.
25 person months
- B.
75 person months
- C.
62.5 person months
- D.
72.5 person months
Attempted by 178 students.