15 men working 8 hours per day complete a piece of work in 18 days. To…

2024

15 men working 8 hours per day complete a piece of work in 18 days. To complete the same work in 6 days, working 12 hours a day, the number of men required will be:

  1. A.

    24 men

  2. B.

    26 men

  3. C.

    28 men

  4. D.

    30 men

Attempted by 6 students.

Show answer & explanation

Correct answer: D

To solve this problem, we use the concept of man-hours. The total work done remains constant. We can equate the product of men, days, and hours for both scenarios: M1 × D1 × H1 = M2 × D2 × H2. Substituting the given values: 15 × 18 × 8 = M2 × 6 × 12. Simplifying the left side gives 2160 man-hours. The right side becomes M2 × 72. Dividing both sides by 72, we find M2 = 30. Therefore, 30 men are required.