45 men can do a job in 16 days. Six days after they started working, 30 more…

2024

45 men can do a job in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work?

  1. A.

    5½ days

  2. B.

    7 days

  3. C.

    5 days

  4. D.

    6 days

Attempted by 5 students.

Show answer & explanation

Correct answer: D

Total work = 45 × 16 = 720 man-days

Work done in 6 days = 45 × 6 = 270
Remaining work = 720 − 270 = 450

Now total men = 45 + 30 = 75

Days required = 450 ÷ 75 = 6 days

Answer: 6 days