What is the full form of the “COCOMO” model?

2026

What is the full form of the “COCOMO” model?

Answer: B. Constructive Cost ModelIn software engineering, an estimation model's acronym is usually built by taking the leading letters or syllables of each word in its full, multi-word name,…

  1. A.

    Cost Constructive Model

  2. B.

    Constructive Cost Model

  3. C.

    Constructive Case Model

  4. D.

    None of the above

Attempted by 136 students.

Show answer & explanation

Correct answer: B

In software engineering, an estimation model's acronym is usually built by taking the leading letters or syllables of each word in its full, multi-word name, in the exact order those words appear in that name.

The model in question has a standard full name built from three words — Constructive, Cost, and Model — taken in that order. Contracting the first syllable of each of the first two words with the third word gives CO + CO + MO, which reproduces the acronym COCOMO exactly.

  • “Cost Constructive Model” swaps the order of the first two words relative to the standard, source-attested name; an acronym contracted from words in this reversed order would not correspond to the name actually used in software-engineering references (e.g., Barry Boehm's cost-estimation literature).

  • “Constructive Case Model” replaces “Cost” with “Case,” a word drawn from a different domain (use cases, test cases) rather than the cost/effort-estimation domain this model addresses.

  • “None of the above” would apply only if none of the three offered word-combinations reproduced the standard full name — which is not the situation here, since one of them does.

Therefore, the word-combination that exactly reconstructs the acronym COCOMO, in the standard order attested by software-engineering references, is “Constructive Cost Model.”