In project management, the 'Critical Path' refers to

2026

In project management, the 'Critical Path' refers to

  1. A.

    The shortest possible time to complete the project

  2. B.

    The sequence of tasks that determines the project's finish date

  3. C.

    The task that are more likely to fail

  4. D.

    The list of tasks that have the low budget

Attempted by 11 students.

Show answer & explanation

Correct answer: B

The Critical Path is the longest sequence of tasks in a project plan that must be completed on time for the project to finish by its deadline.