Which of the following can be used to track the tasks of a project, when the…

2018

Which of the following can be used to track the tasks of a project, when the estimation of task time is fairly uncertain?

  1. A.

    Decision table

  2. B.

    Case tools

  3. C.

    DFD

  4. D.

    PERT

Attempted by 28 students.

Show answer & explanation

Correct answer: D

PERT (Program Evaluation and Review Technique) is used for projects where activity durations are uncertain. It models each task using three time estimates: optimistic (O), most likely (M), and pessimistic (P).

Expected time for a task (TE) is calculated as TE = (O + 4×M + P)

Explore the full course: Niacl Ao It Specialist