According to PUTNAM, the project effort is inversely proportional to the…

2018

According to PUTNAM, the project effort is inversely proportional to the fourth power of the development time. Doubling the development schedule for a 100 Person-Month (PM) project would reduce the project effort to —

  1. A.

    50 PM

  2. B.

    7.16 PM

  3. C.

    25 PM

  4. D.

    6.25 PM

Attempted by 22 students.

Show answer & explanation

Correct answer: D

Putnam's model: Effort ∝ 1