As per software engineering, which of the following order is correct for stages of Risk Management process of a software project?

Attempted by 3 students.

Show answer & explanation

The correct sequence for the Risk Management process in software engineering is: 1. Risk Planning (defining strategy), 2. Risk Identification (finding risks), 3. Risk Analysis (assessing impact/probability), and 4. Risk Monitoring (ongoing oversight). Therefore, the correct order is Planning → Identification → Analysis → Monitoring.