X does a work in 10 days and Y does the same work in 15 days. In how many days…

2017

X does a work in 10 days and Y does the same work in 15 days. In how many days they together will do the same work?

  1. A.

    5 days

  2. B.

    6 days

  3. C.

    8 days

  4. D.

    9 days

Attempted by 39 students.

Show answer & explanation

Correct answer: B

X's rate = 1/10 and Y's rate = 1/15. Together their rate = 1/10 + 1/15 = 1/6, so they finish the work in 6 days.