12 men complete a piece of work in 9 days. The number of days in which 18 men…
2025
12 men complete a piece of work in 9 days. The number of days in which 18 men can complete the same
work is:
- A.
5
- B.
6
- C.
7
- D.
8
Attempted by 58 students.
Show answer & explanation
Correct answer: B
Total work is 12 x 9 = 108 man-days. With 18 men, time required is 108 / 18 = 6 days.