12 men complete a piece of work in 9 days. The number of days in which 18 men…

2025

12 men complete a piece of work in 9 days. The number of days in which 18 men can complete the same
work is:

  1. A.

    5

  2. B.

    6

  3. C.

    7

  4. D.

    8

Attempted by 58 students.

Show answer & explanation

Correct answer: B

Total work is 12 x 9 = 108 man-days. With 18 men, time required is 108 / 18 = 6 days.