Requirements prioritization and negotiation belongs to :

2015

Requirements prioritization and negotiation belongs to :

  1. A.

    Requirements validation

  2. B.

    Requirements elicitation

  3. C.

    Feasibility study

  4. D.

    Requirements reviews

Attempted by 394 students.

Show answer & explanation

Correct answer: B

Answer: Requirements elicitation

Why this is correct: Prioritization and negotiation are performed while gathering and agreeing requirements with stakeholders to resolve conflicts and determine which requirements are most important.

  • Key activities in elicitation: stakeholder interviews, workshops, negotiation, and prioritization techniques (for example, MoSCoW, ranking).

  • Feasibility studies evaluate whether a solution is viable technically, economically, or operationally, but they do not primarily perform stakeholder negotiation of requirements.

  • Validation and reviews check that requirements are correct, complete, and testable after they have been captured; they focus on quality rather than negotiating priorities.

Memory aid: elicitation = collect and agree; validation = confirm; feasibility = can we; reviews = quality check.