Which of the following are the primary objectives of risk monitoring in…
2019
Which of the following are the primary objectives of risk monitoring in software project tracking?
P: To assess whether predicted risks do, in fact, occur
Q: To ensure that risk aversion steps defined for the risk are being properly applied
R: To collect information that can be used for future risk analysis
- A.
Only P and Q
- B.
Only P and R
- C.
Only Q and R
- D.
All of P, Q, R
Attempted by 70 students.
Show answer & explanation
Correct answer: D
Answer: All of P, Q, and R. Risk monitoring serves multiple complementary purposes.
Assess whether predicted risks occur: Track risk triggers, incidents, and changes in probability or impact so you know which risks have materialized.
Ensure risk-aversion steps are applied: Verify that planned mitigation or contingency actions are executed and are effective in managing the risk.
Collect information for future risk analysis: Record outcomes, root causes, metrics, and lessons learned to improve future risk identification, assessment, and response planning.
Tip: Use a risk register, periodic risk-status reports, and lessons-learned reviews to support these monitoring objectives.