Which of the following are the primary objectives of risk monitoring in…

2019

Which of the following are the primary objectives of risk monitoring in software project tracking?

P: To assess whether predicted risks do, in fact, occur

Q: To ensure that risk aversion steps defined for the risk are being properly applied

R: To collect information that can be used for future risk analysis

  1. A.

    Only P and Q

  2. B.

    Only P and R

  3. C.

    Only Q and R

  4. D.

    All of P, Q, R

Attempted by 70 students.

Show answer & explanation

Correct answer: D

Answer: All of P, Q, and R. Risk monitoring serves multiple complementary purposes.

  • Assess whether predicted risks occur: Track risk triggers, incidents, and changes in probability or impact so you know which risks have materialized.

  • Ensure risk-aversion steps are applied: Verify that planned mitigation or contingency actions are executed and are effective in managing the risk.

  • Collect information for future risk analysis: Record outcomes, root causes, metrics, and lessons learned to improve future risk identification, assessment, and response planning.

Tip: Use a risk register, periodic risk-status reports, and lessons-learned reviews to support these monitoring objectives.