Which one of the following is not a risk management technique for managing the…

2014

Which one of the following is not a risk management technique for managing the risk due to unrealistic schedules and budgets?

  1. A.

    Detailed multi source cost and schedule estimation

  2. B.

    Design cost

  3. C.

    Incremental development

  4. D.

    Information hiding

Attempted by 51 students.

Show answer & explanation

Correct answer: D

Information hiding is a software design principle focused on modularity and complexity reduction, not schedule or budget risk management. Techniques like detailed multi-source cost estimation are used to mitigate unrealistic schedules and budgets by improving accuracy.