Which one of the following is not a risk management technique for managing the…
2014
Which one of the following is not a risk management technique for managing the risk due to unrealistic schedules and budgets?
- A.
Detailed multi source cost and schedule estimation
- B.
Design cost
- C.
Incremental development
- D.
Information hiding
Attempted by 51 students.
Show answer & explanation
Correct answer: D
Information hiding is a software design principle focused on modularity and complexity reduction, not schedule or budget risk management. Techniques like detailed multi-source cost estimation are used to mitigate unrealistic schedules and budgets by improving accuracy.