Find the correct sequence of prototype software development model. A. Start B.…

2025

Find the correct sequence of prototype software development model.

A. Start

B. Develop Prototype

C. Deliver to customer

D. Quick Design

E. Quick Play

Choose the correct answer from the options given below:

  1. A.

    A, B, C, D, E

  2. B.

    A, E, D, B, C

  3. C.

    A, B, D, E, C

  4. D.

    A, B, E, D, C

Attempted by 361 students.

Show answer & explanation

Correct answer: C

Correct answer: A, B, D, E, C.

As per the sequence given in the question, the process starts with the initial start stage. Next, the prototype is developed. After developing the prototype, a quick design is prepared and refined. Then the quick play/evaluation step is performed to assess the prototype. Finally, the product is delivered to the customer.

So the correct sequence is:

A. Start → B. Develop Prototype → D. Quick Design → E. Quick Play → C. Deliver to Customer

Hence, the correct answer is:

A, B, D, E, C.

A video solution is available for this question — log in and enroll to watch it.

Explore the full course: Mppsc Assistant Professor