Which one of the following is not a key process area in CMM level 5 ?

2014

Which one of the following is not a key process area in CMM level 5 ?

  1. A.

    Defect prevention

  2. B.

    Process change management

  3. C.

    Software product engineering

  4. D.

    Technology change management

Attempted by 386 students.

Show answer & explanation

Correct answer: C

Answer: Software product engineering is not a CMM Level 5 key process area.

Key process areas at CMM Level 5 (Optimizing) include:

  • Defect prevention — identifies root causes of defects and implements actions to prevent recurrence and improve quality.

  • Technology change management — evaluates, pilots, and deploys new technologies to enhance processes and product capabilities.

  • Process change management — plans and manages changes to organizational processes to achieve measurable improvement.

Why the chosen option is not Level 5:

Software product engineering focuses on technical practices for developing software products and is typically associated with earlier maturity levels where defined engineering processes and practices are established. Level 5 emphasizes organization-wide optimization and continual process improvement, so software product engineering is not categorized as a Level 5 key process area.