A project is planned for an enterprise accounting system with an estimated…

2026

A project is planned for an enterprise accounting system with an estimated size 60 KLOC. The organization applies Basic COCOMO (Semi-Detached Mode with parameters: )

Effort = 3.0 . (KLOC)1.0

Development time = 2.5 . (Effort)1/2

Average cost per person-month (pm) = $10,000

A contingency margin of 10% effort is mandatory

The client demands a detailed schedule if staff is capped at 15 engineers.

If the staff is capped at 15 engineers what is the revised calendar duration?

  1. A.

    20.0 Months

  2. B.

    18.4 Months

  3. C.

    13.2 Months

  4. D.

    22.0 Months

Attempted by 29 students.

Show answer & explanation

Correct answer: C

First, calculate base effort as 3.0 multiplied by 60 KLOC to the power of 1.0, resulting in 180 person-months.

Next, apply the mandatory 10% contingency margin to get a total effort of 198 person-months.

Finally, divide the total effort by the capped staff of 15 engineers to find the revised calendar duration of 13.2 months.

Explore the full course: Mppsc Assistant Professor