A project is planned for an enterprise accounting system with an estimated…

2026

A project is planned for an enterprise accounting system with an estimated size 60 KLOC. The organization applies Basic COCOMO (Semi-Detached Mode with parameters: )

Effort = 3.0 . (KLOC)1.0

Development time = 2.5 . (Effort)1/2

Average cost per person-month (pm) = $10,000

A contingency margin of 10% effort is mandatory

The client demands a detailed schedule if staff is capped at 15 engineers.

Including 10% contingency margin what is the project cost?

  1. A.

    $ 1.80 M

  2. B.

    $ 1.98 M

  3. C.

    $ 2.4 M

  4. D.

    $ 2.36 M

Attempted by 48 students.

Show answer & explanation

Correct answer: B

To determine the project cost, we first calculate the base effort using the Basic COCOMO formula provided: Effort = 3.0 * (KLOC)^1.0. With a size of 60 KLOC, the base effort is 3.0 * 60 = 180 person-months (pm). The problem mandates a 10% contingency margin on effort, so we add this to the base: 180 pm + (10% of 180) = 198 pm. Finally, we calculate the total cost by multiplying the adjusted effort by the average cost per person-month ($10,000). Total Cost = 198 pm * $10,000/pm = $1,980,000 or $1.98 million.",

Explore the full course: Mppsc Assistant Professor