A project is planned for an enterprise accounting system with an estimated…

2026

A project is planned for an enterprise accounting system with an estimated size 60 KLOC. The organization applies Basic COCOMO (Semi-Detached Mode with parameters: )

Effort = 3.0 . (KLOC)1.0

Development time = 2.5 . (Effort)1/2

Average cost per person-month (pm) = $10,000

A contingency margin of 10% effort is mandatory

The client demands a detailed schedule if staff is capped at 15 engineers.

What is the estimated development time in months?

  1. A.

    28 Months

  2. B.

    26 Months

  3. C.

    34 Months

  4. D.

    12 Months

Attempted by 35 students.

Show answer & explanation

Correct answer: C

First, calculate effort using Basic COCOMO Semi-Detached parameters. Effort equals 3.0 multiplied by 60 KLOC to the power of 1.0, resulting in 180 person-months. Next, apply the development time formula: 2.5 times effort to the power of one-half. This yields approximately 33.54 months, which rounds to 34 months as the final estimated development time.