Given CPU time slice of \(2ms\) and following list of processes.…

2019

Given CPU time slice of \(2ms\) and following list of processes.

\(\begin{array}{ccc} \text{Process} & \text{Burst time} & \text{Arrival time} \\ & \text{(ms)} \\ p_1 & 3 & 0 \\ p_2 & 4 & 2 \\ p_3 & 5 & 5 \end{array}\)

Find average turnaround time and average waiting time using round robin CPU scheduling?

  1. A.

    4,0

  2. B.

    5.66,1.66

  3. C.

    5.66,0

  4. D.

    7,2

Attempted by 200 students.

Show answer & explanation

Correct answer: B

Solution:

Use Round Robin scheduling with time quantum = 2 ms.

Gantt chart and remaining times:

0–2: p1 (remaining 1); 2–4: p2 (remaining 2); 4–5: p1 (completes at 5); 5–7: p2 (completes at 7); 7–9: p3 (remaining 3); 9–11: p3 (remaining 1); 11–12: p3 (completes at 12).

  • p1: completion time = 5 ms; turnaround = completion − arrival = 5 − 0 = 5 ms; waiting = turnaround − burst = 5 − 3 = 2 ms.

  • p2: completion time = 7 ms; turnaround = 7 − 2 = 5 ms; waiting = 5 − 4 = 1 ms.

  • p3: completion time = 12 ms; turnaround = 12 − 5 = 7 ms; waiting = 7 − 5 = 2 ms.

Average turnaround time = (5 + 5 + 7) / 3 = 17 / 3 ≈ 5.67 ms.

Average waiting time = (2 + 1 + 2) / 3 = 5 / 3 ≈ 1.67 ms.

Answer: average turnaround ≈ 5.67 ms, average waiting ≈ 1.67 ms.