For a software project, the spiral model was employed. When will the spiral…
2014
For a software project, the spiral model was employed. When will the spiral stop?
- A.
When the software product is retired
- B.
When the software product is released after Beta testing
- C.
When the risk analysis is completed
- D.
After completing five loops
Attempted by 189 students.
Show answer & explanation
Correct answer: A
The Spiral Model is an iterative, risk-driven process that encompasses the entire software lifecycle. Unlike models that stop at delivery, it includes maintenance and evolution phases where risks are continuously managed. Therefore, the spiral continues until the software product is retired completely.