Activities which ensure that the software that has been built, is traceable to…
2009
Activities which ensure that the software that has been built, is traceable to customer requirement is covered as part of
- A.
Verification
- B.
Validation
- C.
Maintenance
- D.
Modeling
Attempted by 76 students.
Show answer & explanation
Correct answer: B
This question distinguishes between Verification and Validation in software engineering. Verification confirms compliance with specifications, whereas Validation ensures the product meets customer requirements and intended use. Traceability to 'customer requirement' specifically aligns with Validation activities.