Consider the following set of processes, with arrival times and the required…

2013

Consider the following set of processes, with arrival times and the required CPU-burst times given in milliseconds.

Process  Arrival Time  Burst Time
   P1        0             4
   P2        2             2
   P3        3             1

What is the sequence in which the processes are completed? Assume round robin scheduling with a time quantum of 2 milliseconds

Answer: B. P2, P1, P3ConceptRound Robin (RR) gives each process a fixed time quantum, then preempts it and sends it to the BACK of a FIFO ready queue. The completion order…

  1. A.

    P1, P2, P3

  2. B.

    P2, P1, P3

  3. C.

    P3, P2, P1

  4. D.

    P2, P3, P1

Attempted by 293 students.

Show answer & explanation

Correct answer: B

Concept

Round Robin (RR) gives each process a fixed time quantum, then preempts it and sends it to the BACK of a FIFO ready queue. The completion order therefore depends entirely on the ready-queue ordering. The one rule that decides this problem: when a running process's quantum EXPIRES at the SAME instant a new process ARRIVES, the standard convention places the NEWLY ARRIVED process into the ready queue FIRST, and the just-preempted process is enqueued AFTER it. This single tie-break determines who runs next.

Application (q = 2 ms)

Given: P1(arrival 0, burst 4), P2(arrival 2, burst 2), P3(arrival 3, burst 1). Simulate step by step:

  1. t = 0–2: Only P1 is present, so P1 runs one quantum. Remaining burst of P1 = 4 − 2 = 2.

  2. t = 2 (tie): P1's quantum expires exactly as P2 arrives. By the convention, the arriving P2 is enqueued first, then preempted P1 behind it. Ready queue → [P2, P1].

  3. t = 2–4: P2 runs (burst 2) and finishes at t = 4. Meanwhile P3 arrives at t = 3 and joins the queue behind P1. Ready queue → [P1, P3].

  4. t = 4–6: P1 runs its remaining 2 ms and finishes at t = 6.

  5. t = 6–7: P3 runs its 1 ms and finishes at t = 7.

Cross-check

Read the finish times in order: P2 at t = 4, then P1 at t = 6, then P3 at t = 7. Completion sequence = P2, P1, P3. The total CPU time also checks out: 4 + 2 + 1 = 7 ms with no idle gap, so the schedule ends exactly at t = 7.

Why the common wrong answer appears

If instead you enqueue the preempted P1 BEFORE the arriving P2 at the t = 2 tie, P1 finishes first and you get P1, P2, P3. That ordering uses the opposite tie-break and is not the convention used by this exam; the accepted answer is P2, P1, P3.