60 men can complete a work in 25 days. One man starts working on it, and one…

2024

60 men can complete a work in 25 days. One man starts working on it, and one more man joins him every day thereafter. In how many days will the work be completed?

  1. A.

    48

  2. B.

    52

  3. C.

    55

  4. D.

    51

Show answer & explanation

Correct answer: C

Concept: When a fixed number of workers works at a constant rate, total work equals workers × days, measured in man-days. If instead the workforce grows by one additional worker every day starting from a single worker, the cumulative man-days completed after n days is the sum of the first n natural numbers, n(n+1)/2 — the standard arithmetic-series identity for a linearly growing workforce.

Application:

  1. Total work required = 60 men × 25 days = 1500 man-days.

  2. One man works on day 1, two men on day 2, and so on, so after n days the cumulative work done is 1 + 2 + 3 + ... + n = n(n+1)/2 man-days.

  3. Set the work done equal to the work required: n(n+1)/2 = 1500, i.e., n(n+1) = 3000.

  4. Test integers near √3000 ≈ 54.8: for n = 54, n(n+1) = 54 × 55 = 2970 (below 3000); for n = 55, n(n+1) = 55 × 56 = 3080 (at or above 3000).

  5. So the cumulative work first reaches 1500 man-days during the 55th day.

Cross-check: after 54 days the work done is 54 × 55 / 2 = 1485 man-days, 15 man-days short of the 1500 needed; on day 55 there are 55 men working, contributing 55 man-days that day alone — comfortably more than the 15 that remain — confirming the job finishes on day 55 and could not have finished a day earlier.

Explore the full course: Infosys Preparation