A contractor agreeing to finish a work in 150 days, employed 75 men each…

20252024202520232024

A contractor agreeing to finish a work in 150 days, employed 75 men each working 8 hours daily. After 90 days, only 2/7 of the work was completed. Increasing the number of men by _____ and each one is working now for 10 hours daily, the work can be completed in time.

  1. A.

    75

  2. B.

    225

  3. C.

    150

  4. D.

    100

Attempted by 34 students.

Show answer & explanation

Correct answer: C

Solution: 3

Total hours worked by 75 men = 90 × 8 = 720

Man-hours put in = 720 × 75 = 54000 man-hours

In so many man-hours, 2/7 of the work is completed

Fraction of work left = 1-2/7 = 5/7

This will take = {54000 × (5/7)}/(2/7) = 135000 man-hours

∵ No. of hours to be worked for remaining days = 60 × 10 = 600

∴ No. of men to be employed = 135000 ÷ 600 = 225

∴ Additional men to be employed = 225 - 75 = 150

Short Trick

We know, (Men1 × Days1 × Hours1)/work1 = (Men2 × Days2 × Hours2)/work2

⇒ (75 × 90 × 8)/(2/7) = (n × 60 × 10)/(5/7)

⇒ n = 225

Hence, increase in number of men = 225 - 75 = 150

Explore the full course: Infosys Preparation