A, B and C can do a piece of work in 20, 15 and 30 days respectively. They…

2023

A, B and C can do a piece of work in 20, 15 and 30 days respectively. They start the work together, but C leaves 6 days before the completion of the work. In how many days is the work done?

  1. A.

    9 days

  2. B.

    6 days

  3. C.

    8 days

  4. D.

    10 days

Attempted by 2 students.

Show answer & explanation

Correct answer: C

Concept: When several people work together on a task, their combined work over the time each one actually works must add up to 1 complete job. If a person can finish the whole work alone in n days, their work rate is 1/n of the job per day, and the amount of work they contribute equals (work rate) × (number of days they actually work).

Application: Let the total time to complete the work be x days. A and B work for the entire x days, since only C leaves early. C leaves 6 days before completion, so C works for (x − 6) days.

  1. A's work rate is 1/20 per day, B's is 1/15 per day, and C's is 1/30 per day.

  2. Total work done: x/20 + x/15 + (x − 6)/30 = 1.

  3. Multiply throughout by 60 (LCM of 20, 15, 30): 3x + 4x + 2(x − 6) = 60.

  4. Simplify: 3x + 4x + 2x − 12 = 60, so 9x = 72.

  5. Solve: x = 8.

Cross-check: With x = 8, A contributes 8/20, B contributes 8/15, and C works for (8 − 6) = 2 days, contributing 2/30. Adding these: 8/20 + 8/15 + 2/30 = 1, confirming the total work equals one complete job.

Explore the full course: Infosys Preparation