Which of the following statement(s) is/are correct regarding software project…

2021

Which of the following statement(s) is/are correct regarding software project management?

I. PERT charts can be derived automatically from Gantt charts.

II. Gantt charts cannot be automatically derived from PERT charts.

  1. A.

    Only I

  2. B.

    Only II

  3. C.

    Both I and II

  4. D.

    Neither I nor II

Attempted by 15 students.

Show answer & explanation

Correct answer: D

Statement I is incorrect because reconstructing a PERT network automatically from a Gantt chart is not feasible without explicit dependency metadata. Statement II is incorrect because standard theory indicates Gantt charts can be derived from PERT networks by mapping activities to a timeline. Therefore, neither statement is correct regarding software project management chart conversions.