Who is the slowest among the three builders A, B, and C? Statements: I. A and…

2023

Who is the slowest among the three builders A, B, and C?

Statements:

I. A and B together take 5 hours to build a wall.

II. A, B, and C together can build the wall in 3 hours.

  1. A.

    Statement I alone is sufficient.

  2. B.

    Statement II alone is sufficient.

  3. C.

    Both the statements, when put together, are sufficient.

  4. D.

    Both the statements, put together, are not sufficient.

Attempted by 1 students.

Show answer & explanation

Correct answer: D

Concept: A data-sufficiency statement (or combination of statements) is sufficient only if it pins down a single, unique answer to the question asked — not merely a plausible one. For a work-rate problem, the governing identity is rate = 1 / time, and when two or more people work together their combined rate is simply the sum of their individual rates.

Application: let the hourly work rates of A, B, and C (fraction of the wall completed per hour) be a, b, and c.

  1. Statement I gives the combined rate of A and B: a + b = 1/5.

  2. Statement II gives the combined rate of all three together: a + b + c = 1/3.

  3. Subtracting the first equation from the second isolates C's individual rate: c = 1/3 - 1/5 = 2/15, so C alone would take 7.5 hours to build the wall.

  4. However, a + b = 1/5 is only a single combined figure. It does not split into unique individual values of a and b, so A and B's individual rates — and hence which of the two is slower — remain undetermined even after using both statements together.

Cross-check: two different splits of a + b = 1/5 both satisfy the statements but hand the wall to a different 'slowest builder' each time.

Split

A's time

B's time

C's time

Slowest builder

Split 1

6 hours

30 hours

7.5 hours

B

Split 2

10 hours

10 hours

7.5 hours

A and B (tied)

Both splits satisfy a + b = 1/5 (Statement I) and c = 2/15 (both statements together), yet they name a different builder as slowest. Since two scenarios that are both consistent with the given statements produce different answers, the two statements together fail to fix a unique answer.

It can also be shown that C alone can never be the unique slowest: if both A and B individually took less than 7.5 hours each, their combined rate would exceed 1/5, contradicting Statement I. So the slowest builder is always A or B — but exactly which one depends entirely on the unknown split, so the question still cannot be answered. Both the statements, put together, are not sufficient.

Explore the full course: Deloitte Nla

Loading lesson…