A team of 40 employees were appointed to finish the project of a shopping mall…

2024

A team of 40 employees were appointed to finish the project of a shopping mall in 200 days. How many more employees should be appointed to finish it in 80 days?

  1. A.

    80

  2. B.

    60

  3. C.

    75

  4. D.

    100

Attempted by 2 students.

Show answer & explanation

Correct answer: B

Concept: When every employee works at the same steady rate, the total amount of work in a project is fixed. So Employees × Days = Constant (the total man-days). If the deadline changes, that same fixed amount of work must be redistributed across the new number of days, so for a fixed job, the number of employees needed and the number of days available vary inversely.

  1. Find the total work for the job in man-days: 40 employees × 200 days = 8,000 man-days.

  2. Find how many employees are needed to complete this same 8,000 man-days of work in 80 days: 8,000 ÷ 80 = 100 employees.

  3. The question asks for the additional employees needed, not the new total, so subtract the original team: 100 − 40 = 60.

Cross-check: with 100 employees working for 80 days, total work done = 100 × 80 = 8,000 man-days, which exactly matches the original 40 × 200 = 8,000 man-days — confirming the total (and hence the additional 60) is correct.

Hence, 60 more employees must be appointed.