A 4-stage pipeline has the stage delays as 150, 120, 160 and 140 nanoseconds…

2004

A 4-stage pipeline has the stage delays as 150, 120, 160 and 140 nanoseconds respectively. Registers that are used between the stages have a delay of 5 nanoseconds each. Assuming constant clocking rate, the total time taken to process 1000 data items on this pipeline will be

Answer: C. 165.5 microsecondsKey insight: the clock period must accommodate the slowest stage plus the register delay. Find the maximum stage delay: max(150, 120, 160, 140) = 160 ns. Add…

  1. A.

    120.4 microseconds

  2. B.

    160.5 microseconds

  3. C.

    165.5 microseconds

  4. D.

    590.0 microseconds

Attempted by 235 students.

Show answer & explanation

Correct answer: C

Key insight: the clock period must accommodate the slowest stage plus the register delay.

  • Find the maximum stage delay: max(150, 120, 160, 140) = 160 ns.

  • Add the register delay to get the clock period: 160 ns + 5 ns = 165 ns per cycle.

  • Compute the number of clock cycles to process 1000 items in a 4-stage pipeline: cycles = stages + items - 1 = 4 + 1000 - 1 = 1003 cycles.

  • Total time = 1003 cycles × 165 ns = 165,495 ns = 165.495 microseconds ≈ 165.5 microseconds.

Final answer: 165.495 microseconds (approximately 165.5 microseconds).