Consider a job scheduling problem with four jobs J₁, J₂, J₃ and J₄ with corresponding deadlines : (d₁, d₂, d₃, d₄) = (4, 2, 4, 2)
Which of the following is not a feasible schedule without violating any job deadline?

Answer: B. J₄, J₁, J₂, J₃Check each job position against its deadline. In J4, J1, J2, J3, job J2 is scheduled third even though its deadline is 2, so that schedule is not feasible.

  1. A.

    J₂, J₄, J₁, J₃

  2. B.

    J₄, J₁, J₂, J₃

  3. C.

    J₄, J₂, J₁, J₃

  4. D.

    J₄, J₂, J₃, J₁

Attempted by 307 students.

Show answer & explanation

Correct answer: B

Check each job position against its deadline. In J4, J1, J2, J3, job J2 is scheduled third even though its deadline is 2, so that schedule is not feasible.