A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. How long would A take separately to do the same work?

Answer: B. 30 days 30 दिनSolution: Find A's time using work rates. Let A, B, C denote the fractions of the work they do per day. From the given: A + B = 1/12, B + C = 1/15, C + A =…

  1. A.

    40 days
    40 दिन

  2. B.

    30 days
    30 दिन

  3. C.

    20 days
    20 दिन

  4. D.

    10 days
    10 दिन

Attempted by 7 students.

Show answer & explanation

Correct answer: B

Solution: Find A's time using work rates.

  • Let A, B, C denote the fractions of the work they do per day.

  • From the given: A + B = 1/12, B + C = 1/15, C + A = 1/20.

  • Add the three equations: 2(A + B + C) = 1/12 + 1/15 + 1/20 = 1/5, so A + B + C = 1/10.

  • Then A = (A + B + C) - (B + C) = 1/10 - 1/15 = 1/30.

  • So A does the whole work in 30 days.