A team of 40 employees were appointed to finish the project of a shopping mall…

2024

A team of 40 employees were appointed to finish the project of a shopping mall in 200 days. How many more employees should be appointed to finish it in 80 days?

Answer: B. 60Concept: When every employee works at the same steady rate, the total amount of work in a project is fixed. So Employees × Days = Constant (the total…

  1. A.

    80

  2. B.

    60

  3. C.

    75

  4. D.

    100

Attempted by 19 students.

Show answer & explanation

Correct answer: B

Concept: When every employee works at the same steady rate, the total amount of work in a project is fixed. So Employees × Days = Constant (the total man-days). If the deadline changes, that same fixed amount of work must be redistributed across the new number of days, so for a fixed job, the number of employees needed and the number of days available vary inversely.

  1. Find the total work for the job in man-days: 40 employees × 200 days = 8,000 man-days.

  2. Find how many employees are needed to complete this same 8,000 man-days of work in 80 days: 8,000 ÷ 80 = 100 employees.

  3. The question asks for the additional employees needed, not the new total, so subtract the original team: 100 − 40 = 60.

Cross-check: with 100 employees working for 80 days, total work done = 100 × 80 = 8,000 man-days, which exactly matches the original 40 × 200 = 8,000 man-days — confirming the total (and hence the additional 60) is correct.

Hence, 60 more employees must be appointed.