After working for 6 days, Ashok finds that only 1/3 rd of the work has been…

2024

After working for 6 days, Ashok finds that only 1/3 rd of the work has been done. He employs Ravi who is 60% as efficient as Ashok. How many days more would Ravi take to complete the work?

Answer: C. 20 daysKey insight: convert work done into daily rates, find the remaining work, then divide by Ravi's rate. After 6 days Ashok has completed 1/3 of the work, so…

  1. A.

    19 days

  2. B.

    10 days

  3. C.

    20 days

  4. D.

    12 days

Attempted by 44 students.

Show answer & explanation

Correct answer: C

Key insight: convert work done into daily rates, find the remaining work, then divide by Ravi's rate.

  • After 6 days Ashok has completed 1/3 of the work, so Ashok's daily rate = (1/3) ÷ 6 = 1/18 of the work per day.

  • Ravi is 60% as efficient as Ashok, so Ravi's daily rate = 0.6 × 1/18 = 1/30 of the work per day.

  • Remaining work = 1 − 1/3 = 2/3.

  • Time required for Ravi = (remaining work) ÷ (Ravi's rate) = (2/3) ÷ (1/30) = 20 days.

Answer: 20 days