P can lay railways track between two stations in 16 days. Q can do the same…

2023

P can lay railways track between two stations in 16 days. Q can do the same job in 12 days. With the help of R, they complete the job in 4 days. How much days does it take for R alone to complete the work ?

  1. A.

    9(3/5) days

  2. B.

    9(1/5) days

  3. C.

    9(2/5) days

  4. D.

    10 days

Attempted by 3 students.

Show answer & explanation

Correct answer: A

Step-by-Step Solution

  1. Identify Individual Work Rates:

    • P's rate of work = 1/16 of the job per day.

    • Q's rate of work = 1/12 of the job per day.

    • Combined rate of P, Q, and R = 1/4 of the job per day.

  2. Calculate R's Work Rate:

    • R's rate = (Combined rate of P, Q, and R) - (P's rate + Q's rate).

    • R's rate = 1/4 - (1/16 + 1/12).

    • Find the least common multiple for 4, 16, and 12, which is 48.

    • R's rate = 12/48 - (3/48 + 4/48).

    • R's rate = 12/48 - 7/48 = 5/48 of the job per day.

  3. Find Time Taken by R Alone:

    • Time = 1 / (Rate) = 1 / (5/48) = 48/5 days.

    • 48/5 days = 9 and 3/5 days.