Three men finish painting a wall in 8 days. Four boys do the same job in 7 days. In how many days will 2 men and 2 boys working together paint two such walls of the same size ?

  1. A.

    11 12/11 days

  2. B.

    12 12/13 days

  3. C.

    16 days

  4. D.

    12 days

Attempted by 6 students.

Show answer & explanation

Correct answer: B

Key facts: three men finish one wall in 8 days and four boys finish one wall in 7 days.

  • One man's one-day work = 1/(3×8) = 1/24.

  • One boy's one-day work = 1/(4×7) = 1/28.

  • Two men and two boys' combined one-day work = 2×(1/24) + 2×(1/28) = 13/84.

  • Time to paint one wall = 1 ÷ (13/84) = 84/13 days. For two walls: 2×(84/13) = 168/13 = 12 12/13 days.

Answer: 168/13 = 12 12/13 days.