It was calculated that 75 men could complete a piece of work in 20 days. When…

20232025202320232023

It was calculated that 75 men could complete a piece of work in 20 days. When work was scheduled to commence, it was found necessary to send 25 men to another project. How long it will take to complete the work?

  1. A.

    35

  2. B.

    25

  3. C.

    30

  4. D.

    45

Attempted by 42 students.

Show answer & explanation

Correct answer: C

Solution: 3

Amount of work = 75 × 20 = 1500 man-days

25 men are sent away, so men left = 75 – 25 = 50

Hence, days taken to finish work = 1500 ÷ 50 = 30 days