If P can do a work in 6 days and Q can do the same work in 8 days. If R who…

2023

If P can do a work in 6 days and Q can do the same work in 8 days. If R who can do the same work in 12 days, joins them, then the work will be completed in how many days?

  1. A.

    7/3 days

  2. B.

    8/3 days

  3. C.

    10/3 days

  4. D.

    11/3 days

Attempted by 61 students.

Show answer & explanation

Correct answer: B

Solution:

P's rate = 1/6 work per day, Q's rate = 1/8 work per day, R's rate = 1/12 work per day. Combined rate = 1/6 + 1/8 + 1/12.

Compute using LCM 24: 1/6 = 4/24, 1/8 = 3/24, 1/12 = 2/24. So combined rate = (4 + 3 + 2)/24 = 9/24 = 3/8 work per day.

Time to finish the work = reciprocal of rate = 1 ÷ (3/8) = 8/3 days.

Final answer: 8/3 days (about 2 2/3 days).