If P can do a work in 6 days and Q can do the same work in 8 days. If R who can do the same work in 12 days, joins them, then the work will be completed in how many days?

  1. A.

    7/3 days

  2. B.

    8/3 days

  3. C.

    10/3 days

  4. D.

    11/3 days