12 persons can complete the work in 18 days. After working for 6 days, 4 more persons are added to complete the work fast. In how many more days will they complete the work?

  1. A.

    6 days

  2. B.

    9 days

  3. C.

    12 days

  4. D.

    14 days

Attempted by 44 students.

Show answer & explanation

Correct answer: B

Step-by-step solution:

  • Compute total work in person-days: 12 persons × 18 days = 216 person-days.

  • Work done in the first 6 days by 12 persons: 12 × 6 = 72 person-days.

  • Remaining work: 216 − 72 = 144 person-days.

  • After adding 4 persons there are 16 persons. Days required = remaining work ÷ number of persons = 144 ÷ 16 = 9 days.

Final answer: 9 days.