Assume that the following jobs are to be executed on a single processor system. The jobs are assumed to have arrived at time t = 0⁺ and in the order P, Q, R, S, T; calculate the departure time (completion time) for job P if scheduling is round robin with time slice 1.

Job Id

CPU Burst Time

P

4

Q

1

R

8

S

1

T

2

  1. A.

    4

  2. B.

    10

  3. C.

    11

  4. D.

    12

  5. E.

    None of the above