For the processes listed in the following table, which of the following…

PYQ GATE 2015

For the processes listed in the following table, which of the following scheduling schemes will give the lowest average turnaround time?

Process

Arrival Time

Processing Time

A

0

3

B

1

6

C

4

4

D

6

2

  1. A.

    First Come First Serve

  2. B.

    Non-preemptive Shortest Job First

  3. C.

    Shortest Remaining Time

  4. D.

    Round Robin with Quantum value two