45 men can complete a work in 16 days. Six days after they started working, 30…
TCS · 2024
45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. In how many days the total work will be completed ?
- A.
12
- B.
8
- C.
15
- D.
14