A alone can do 2/3rd of the work in 12 days . B alone can do the 1/4th of the…

TCS · 2025

A alone can do 2/3rd of the work in 12 days . B alone can do the 1/4th of the work in 6 days . Working together A , B and C complete it in 8 days . What part of the work will be completed by C in 4 days ?

  1. A.

    1/9

  2. B.

    2/7

  3. C.

    1/6

  4. D.

    3/7