Abu does a work in 15 days whereas Basu and Cornel does the same work in 12…
TCS · 2025
Abu does a work in 15 days whereas Basu and Cornel does the same work in 12 and 20 days respectively. All the three started work together. Cornel left the work after 2 days and Basu left 3 days before competition of work. Find the total number of days in which work will be completed?
- A.
7(1/2)
- B.
7(1/4)
- C.
7(1/3)
- D.
7(2/3)